The Minimum Revenue Guarantee Level for PPP Projects Based on Real Option

Expand
  • College of Management and Economics, Tianjin University, Tianjin 300072, China

Received date: 2016-12-13

  Revised date: 2017-04-11

  Online published: 2018-09-20

Abstract

PPP(Public-Private Partnership)is adopted throughout the world for delivering public infrastructures. However, the implement has not been without trouble because of the uncertainty of revenue. The insufficiency of revenue results in the failure of many PPP projects, which discourages the private investors. Government compensation becomes indispensable to stimulate private investment and ensures the success in PPP projects.
One of the most common forms of government compensation is the minimum revenue guarantee. Minimum revenue guarantee means the low demand risk is undertaken by government. Many researchers have advocated toll revenue cap so as to balance the risk and benefit. However, the government undertakes the complete low demand risk while shares only part of the over revenue. This leads to inappropriate risk and benefit sharing and over-guarantee occurs a lot in PPP projects. To settle these problems, setting the reasonable minimum revenue guarantee level is extremely significant.
In this paper, a model is established to estimate the minimum revenue guarantee level from the perspective of reasonable risk and benefit sharing. The value of the minimum revenue guarantee should equal to the value that toll revenue cap brings to the government. Binomial Lattice, one of the main methods of Real Option, is used to calculate the value. Because of the uncertainty, the demand varies from year to year. The value of the toll revenue cap option at n year could be estimated by the rise and fall probability of demand, the revenue sharing proportion and the cap. The value at n-1 year is the discounted value of weighted average at t=n year. Similarly, the value at the beginning can be estimated. The value of the minimum revenue guarantee option could be estimated in the same way. The minimum guarantee level should make the value of the two options the same. Then, a numerical example is provided to explain how to estimate minimum revenue guarantee level.
The studying results show that the minimum revenue guarantee level should not be fixed during the operation period. To balance the risk and benefit of government, it is mainly affected by the value of toll revenue cap which is estimated by lots of factors. This model could not only contribute to setting guarantee level, but also favor the intention of risk and benefit sharing in PPP projects. It greatly makes for solving the over-guarantee trouble that has caused huge loss for government.

Cite this article

WANG Xiu-qin, KAN Meng-ying, ZHANG Yi-hong . The Minimum Revenue Guarantee Level for PPP Projects Based on Real Option[J]. Chinese Journal of Management Science, 2018 , 26(7) : 40 -46 . DOI: 10.16381/j.cnki.issn1003-207x.2018.07.005

References

[1] Sharma C. Determinants of PPP in infrastructure in developing economies[J]. Transforming Government People Process and Policy, 2012, 6(2):149-166.

[2] 柯永建,王守清,陈炳泉. 私营资本参与基础设施PPP项目的政府激励措施[J]. 清华大学学报(自然科学版), 2009,49(9):1480-1483.

[3] World Bank, Asian Development Bank, Inter-American Development Bank. Public-private partnerships reference guide[M]. 2014:14.

[4] Ke Yongjian, Liu Xinping, Wang Shouqing. Equitable financial evaluation method for public-private partnership projects[J]. Tsinghua Science & Technology, 2008, 13(5):702-707.

[5] Espinoza R D. Separating project risk from the time value of money:A step toward integration of risk management and valuation of infrastructure investments[J]. International Journal of Project Management, 2014, 32(6):1056-1072.

[6] Chan A P C, Lam P T I, Chan D W M, et al. Critical success factors for PPPs in infrastructure developments:Chinese perspective[J]. Journal of Construction Engineering & Management, 2010, 136(5):484-494.

[7] Soomro M A, Zhang Xueqing. Roles of private-sector partners in transportation public-private partnership failures[J]. Journal of Management in Engineering, 2013, 31(4):04014056.

[8] Chiang Y H, Cheng E W L. Perception of financial institutions toward financing PFI projects in Hong Kong[J]. Journal of Construction Engineering & Management, 2009, 135:833-840.

[9] 吴孝灵, 刘小峰, 周晶,等. 基于私人过度自信的PPP项目最优补偿契约设计与选择[J]. 中国管理科学, 2016, 24(11):29-39.

[10] 徐飞, 宋波. 公私合作制(PPP)项目的政府动态激励与监督机制[J]. 中国管理科学, 2010, 18(3):165-173.

[11] Arboleda C A, Abraham D M. Evaluation of flexibility in capital investments of infrastructure systems[J]. Engineering, Construction and Architectural Management, 2006, 13(3):254-274.

[12] Osman H, Marzouk M, Ali M. Valuation of minimum revenue guarantees for PPP wastewater treatment plants[C]//Proceedings of ASCE Construction Research Congress, West Lafayette, Indiana, US, May 21-23, 2012.

[13] 刘婷,赵桐,王守清. 基于案例的我国PPP项目再谈判情况研究[J]. 建筑经济,2016,37(9):31-34.

[14] Adetunji O, Owolabi A. Real options and government supports to PPP infrastructure investments:An empirical study[J]//Journal of Modern Accounting and Auditing, 2017,13(5):196-215.

[15] Chiara N, Asce S M, Garvin M J, et al. Valuing simple multiple-exercise real options in infrastructure projects[J]. Journal of Infrastructure Systems, 2007, 13(2):97-104.

[16] Nugroho L A. Franchise revenue guarantee valuation:Real options approach[J]. Journal of Financial Risk Management, 2015, 4(1):26-39.

[17] 高峰,郭菊娥,龚利.基础设施项目政府担保的双障碍期权价值研究[J].管理工程学报, 2008, 22(3):19-23.

[18] Liu Jicai, Cheah C Y J. Real option application in PPP/PFI project negotiation[J]. Construction Management and Economics, 2009, 27(4):331-342.

[19] Iyer K C, Sagheer M. A real options based traffic risk mitigation model for build-operate-transfer highway projects in India[J]. Construction Management and Economics, 2011, 29(8):771-779.

[20] Jun J. Appraisal of combined agreements in BOT project finance:Focused on minimum revenue guarantee and revenue cap agreements[J]. International Journal of Strategic Property Management, 2010, 14(2):139-155.

[21] Wang Yuanqing, Li Zihua, Gao Yanan. Minimum revenue guarantee and toll revenue cap optimization for PPP highways:Pareto optimal state approach[J]. Baltic Journal of Road & Bridge Engineering, 2015, 10(4):365-371.

[22] Ashuri B, Kashani H, Molenaar K R, et al. A valuation model for choosing the optimal minimum revenue guarantee (MRG) in a highway project:A feal-option approach[C]//Proceedings of the Construction Research Congress, Banff, Acberta, Canada, May 8-10, 2010.

[23] Carbonara N, Costantino N, Pellegrino R. Revenue guarantee in public-private partnerships:A fair risk allocation model[J]. Construction Management & Economics, 2014, 32(4):403-415.

[24] Song Jinbo, Jin Lulu, Dong Wanli. Excess revenue allocation for build-operate-transfer highway projects[J]. Journal of Transport Economics & Policy, 2016, 50(3):304-324.

[25] 吴孝灵, 周晶, 彭以忱, 等. 基于公私博弈的PPP项目政府补偿机制研究[J]. 中国管理科学, 2013, 21(S1):198-204.

[26] Kokkaew N, Sunkpho J, Sampim T. Risk flexibility theory as an economic decision-making support tool for complex engineering systems[C]//Proceedings of the 14th International Conference on Computing in Civil and Building Engineering, Moscow, Russia, June 27-29, 2012.

[27] Arboleda C A, Abraham D M. Evaluation of flexibility in capital investments of infrastructure systems[J]. Engineering Construction & Architectural Management, 2006, 13(3):254-274.

[28] Martins J, Marques R C, Cruz C O. Real options in infrastructure:Revisiting the literature[J]. Journal of Infrastructure Systems, 2015, 21(1):04014026.

[29] 赵秀云,李敏强,寇纪淞.风险项目投资决策与实物期权估价方法[J].系统工程学报,2000,15(3):243-246.

[30] Huang Y L, Chou S P. Valuation of the minimum revenue guarantee and the option to abandon in BOT infrastructure projects[J]. Construction Management and Economics, 2006, 24(4):379-389.

[31] Power G J, Burris M, Vadali S, et al. Valuation of strategic options in public-private partnerships[J]. Transportation Research Part A:Policy and Practice, 2016, 90:50-68.
Outlines

/